Re-floor-mation Completed

Between Mar 1 and Apr 14, I completed the process of removing the old subfloor and replacing it with a new, lower subfloor, as described in my Floor Mark 2 post.  All told, I spent:

  • 89 hours constructing the original floor (2019-10-08 to 2019-11-21)
  • 12.5 hours in mitigation/drying efforts (2019-11-21 to 2019-12-13)
  • 32 hours removing the original floor (2020-03-02 to 2020-04-06)
  • 59 hours installing the new floor (2020-03-02 to 2020-04-14)

I finished getting the new joists installed:

Floor joists
Final section of new floor joists

 

 

…and reinstalled the subfloor the same day (although I didn’t get the photo until the next morning):

New flooring
New flooring finished

 

Then, I was ready to start on SIPs.  More on that in the next post.

One thought on “Re-floor-mation Completed”

Leave a Reply

Your email address will not be published. Required fields are marked *