See Foam Spray

When I talk about “foam spray” I’m not trying to conjure images of the (original) Little Mermaid, and I’m not even talking about the cans of compressed foam material that came with my SIP order.  What I’m actually referring to is the rather unexpected spray of small foam particles that I’ve been contending with since I began working with my new SIPs.

Murus panel router

Each SIP needs to be routed out at the top and bottom and at every edge where structural components (such as window frames) need to be added.  Murus Co., my SIP vendor, offers a cleverly designed tool to rout out the foam to the exact depth of a 2×6 member.

 

What they don’t tell you is that when you do this, it snows.  Not the cold stuff, because it’s snowing insulation after all.  Do not try this on a windy day.  To help with this, I decided I needed to make a separate tool, which is a foam-catcher.  I plug the shop vac directly into the end of this, and it does help contain the foam spray.

Foam spray containment boxHowever, the best solution so far has been actually getting up the first walls.  Once I had my corner in place (with some help from my more experienced neighbor Dane) I was able to get a few panels in place myself.  This shielded from enough of the wind that further routing inside the partial walls was relatively contained.

First four SIPs
Apr 19: First four SIPs installed

After this, I began installing more SIPs on the east wall.  By the end of the day on Apr 20, I had seven SIPs in place and I thought all was going rather well.

Apr 20: Seven SIPs

That was until I woke up on Tuesday morning and realized that I had forgotten to include the structural members in the center of the east wall which would provide the primary vertical support for the roof ridge beam.  Ugh…  So after attempting to pull out the ring-shank nails unsuccessfully, and a trip to the store to pick up a better tool, I was thrilled that I was actually able to pull out all of the nails rather easily.  Getting the panel loose from the foam which had glued it in place was a bit more difficult.  (Okay, a lot more difficult, it took longer to get it free than it took to get out the ~2 dozen nails.)  But eventually I was able to take it down, leaving me back at six nearly-completed SIPs on Apr 21.

Apr 21: Six SIPs

The SIP I removed (on the top of the wrapped stack) is still in relatively good condition; I was worried that I was going to have to cut it loose, but this turned out not to be necessary.  nevertheless, out of an abundance of caution, I’m going to put it aside for use in a non-load-critical location, probably on the second floor, just in case the process did invisible damage to the structure.  I’ll take a brand new SIP to replace it in this structural location on the first floor.

Unfortunately, the weather has now gotten too windy, snowy, rainy, and cold to proceed for a few days.  (The foam is supposed to be applied at temperatures over 50°F, and I doubt I could manage to hold onto a 4×8 SIP with 20 mile-per-hour winds.)  So I’m working on some other home projects for a few days, and getting this blog up to date!

 

Re-floor-mation Completed

Between Mar 1 and Apr 14, I completed the process of removing the old subfloor and replacing it with a new, lower subfloor, as described in my Floor Mark 2 post.  All told, I spent:

  • 89 hours constructing the original floor (2019-10-08 to 2019-11-21)
  • 12.5 hours in mitigation/drying efforts (2019-11-21 to 2019-12-13)
  • 32 hours removing the original floor (2020-03-02 to 2020-04-06)
  • 59 hours installing the new floor (2020-03-02 to 2020-04-14)

I finished getting the new joists installed:

Floor joists
Final section of new floor joists

 

 

…and reinstalled the subfloor the same day (although I didn’t get the photo until the next morning):

New flooring
New flooring finished

 

Then, I was ready to start on SIPs.  More on that in the next post.

Construction Becomes My Full-Time Job

Friday, Apr 3 was my last day with my previous full-time employer.  While many in the country (and some at my former employer) are being laid off due to COVID-19, this was a voluntary departure for me.  I gave notice on March 16, well before the future magnitude of the economic impact of COVID-19 in the US was clear to the average citizen.  (I kind of had an inkling, though many aspects of the timing and time course of events were still surprising.)

This now makes our little construction company my full time job.  I scheduled all of this to (supposedly) correspond with the delivery of my SIPs (structural insulated panels).  However, because of weekends taken delivering Raederle to and recovering her from a trip to Costa Rica, I lost a bit of the time I expected to have for removing the old floor (“deflooring” as I’ve been calling it) and reinstalling the new one.  Then, in a pleasant surprise, my SIPs arrived more than a week earlier than expected on Mar 25.  So now I’m a little “behind the eight ball“.  (Q: “How will house construction go?”  A: “Without a doubt”)

I want to try to update more often so that the rapid progress can be reported, but I have to balance that against getting the most out of the usable working hours.  So we will see how that goes.

New joists
I spent free time over the winter cutting new joists (Jan 3)
Floor deconstruction
When the weather looked good I began deflooring the house (Mar 25)
Removing moldly boards
As I suspected, the water during the winter had grown some mold (Mar 31)
Deflooring in progress
Deflooring in progress, most of the rockwool removed (Mar 26)
Floor stripped down
Much of the floor stripped down to PT plywood (Apr 1)
New joists installed
First row of new joists installed between I-beam and rim joists, and leveled (Apr 4)
Reinstalled subfloor
First portion of subfloor reinstalled over new joists (Apr 4)

 

And Now, Your Feature Presentation

I’ve been gradually building up a summary of the main features that I plan to include in the Little Rental House.  Some of these will go in with the first build; others might be “nice-to-haves” that get added once the home is actually ready for occupancy.

  • Accessible
    • ADA-compliant parking space
    • ADA-compliant bathroom, kitchen, living areas
    • ADA-compliant entrance ramps, etc.
  • Efficient resource use for heating and cooling
    • Walls, ceiling, and floor all insulated to better than R-40.
    • Double (or maybe triple) glazed windows for heat retention.
    • Heated with air-source heat pump to minimize power required.
    • Heat-recovery ventilator to provide fresh air with minimum heat loss.
    • Hot water heating inside heated space (reduces heat loss)
    • Drain water heat recovery unit
  • Minimum water footprint
    • Rainwater collection with filtration and UV sterilization
    • Downcycling of greywater for toilet flushing
  • Minimum power requirements
    • Low-voltage LED lighting used throughout to save power (< 0.25kWh/day)
    • DC refrigerator (< 0.7kWh/day)
    • Direct outlets for DC appliances (24V, 5V USB)
    • Two stage water heating with ultra-insulated storage (30 gal, est. < 0.5kWh/day) plus on demand system for large volume use (AC only)
    • Water pumping using low power, low voltage DC pumps (< 0.1kWh/day including sterilization)
    • Heat recovery from waste water (bathtub, clothes washer, sinks)
  • Grid-flexible solar power generation
    • Battery storage (about 10 kWh) for approximately 6 days including hot water, up to 2 days with constant heating.
    • Online inverter provides whole-house “uninterruptible” power supply

The City of Ithaca and Town of Ithaca are working on a new joint “energy code supplement” to encourage green building.  New construction should get a minimum of 6 “points” in their system.  My rough calculation for the proposed home is 11 points:

  • EE1: air source heat pump = 3 points
  • AI1: smaller building size = 2 points (under 1120 sq ft)
  • AI2: heating system in heated space = 1 point
  • AI5: modest window-to-wall ratio (13%) = 1 point
  • RE1: on-site renewable electric = 3 points (2350 kWh/year / 648 sf > 3.6)
  • OP4: meet NYStred Code-2020 Version 1.0 = 2 points (maybe, complex to evaluate)

Do Over: Floor, Mark 2

Since part of my goal is to document the process of construction, it’s time to declare my first major oops.  Maybe this will save someone else from doing something pointless and wasting time and money.  Sigh.

I am not happy with my floor implementation.  It feels solid and well insulated, but there are numerous issues with it that have led me to decide to start over.  In the end I expect I’ll waste about $600 and maybe a week worth of labor, but I think the end result will be better.

First, I wanted to nominate Terry S. for the “you called it” award on water.  Even with one layer of house wrap, fully taped, and not one but two 30×30′ tarps tented up and covering the floor, it is still basically raining inside every time the weather turns warm or launches into a downpour that melts the snow.  While I’ve had builders assure me that the water will just run through, and it will dry out, and it will all be fine, I’m not certain enough to trust putting the rest of the house on it without checking.  And checking means starting to peel up the subfloor so I can look inside, and once I start that if it looks bad, I’m going to need to redo things anyway.

But that by itself could just be a bit of maintenance in the spring.  No, there are a lot of other problems that have combined to make we want to start over on the flooring.

  • Elevation: because of the additional 6″ of height added by the flooring (which would of course have been there with SIPs as well) making the home accessible is turning out to be a lot more difficult that I would have liked.
  • Structural: the bottom inlet nailers for the wall SIPs would have been mounted to the floor stack, which itself is not really a tested structural element.  (SIPs would have been better, but not ideal.)
  • Levelness: in my rush to get the floor in place before the winter, I didn’t do a great job of shimming around the I-beams to bring the rim joist level up to the I-beam level.
  • Mechanicals: with the insulation sandwiched between the two layers, any mechanicals (plumbing and electric) going through to the basement would have to be cut through both layers of board plus insulation.
  • Water damage: may or may not have occurred.

So, I’ve come up with a new plan, and by choosing to go forward despite the possibility that the current floor is “sound” (with respect to the water – all the other issues would still stand), I have the opportunity to implement a good fraction of it (the first three steps) from inside the basement during the winter, so there will be less of a scramble to do the added work when spring comes.

  1. Cut 2×8 joists to fit between (and perpendicular to) the I-beams.  Notch these at each to a depth closely matched to the flange thickness of the I-beam, so that when assembled the top of the joist and I-beam will be flush.  (This addresses the elevation issue: subfloor will eventually sit 6″ lower.)
  2. Remove screws from bottom of current assembly.
  3. Insulate rim joists.  (May need to wait depending on other steps.)
  4. Strip off and stack the subfloor boards.  (If the subfloor was water damaged, then it would have needed to be replaced anyway, but if it’s OK I hope to be able to reuse it since I’ll be screwing back down to identically aligned joists.)
  5. Pull out and stack the rockwool for reuse.
  6. Strip off the 2×6 and 2×4 joists and the PIR.  (We’ll have to see what order of operations works best for this.)  Stack PIR for reuse.
  7. Strip off and stack the PT plywood.  (Need to determine if it can be reused elsewhere in the project; otherwise perhaps it will show up on Craigslist.)
  8. Correct the shims on the rim joists to as near flush with I-beams as practical.  (This addresses the levelness issue.)
  9. Finish mounting east and west joists with joist hangars from rim joists.
  10. Reinstall subfloor.
  11. Put off reinstalling insulation until after mechanical work is done.  (This addresses mechanicals issue.)
  12. Install inlet nailers with structural screws to rim joists.  (This addresses structural issue, and is the first step of the work I would have started in the spring anyway.)

It seems like a lot of steps, but it feels like I should be able to do most of them in less than a day.  So far I’ve completed the first eight of the 7′ joists and eight of the 4′ joists, and about 20% of the screw removal.  While I was at it, I also restacked some of the stored lumber in the basement so that it’s not directly under the drip edges.  The time spent has been about 3 hours so far.

For photos see my Apr 5 post.

Wow, I’m Floored!

For the last couple of weeks it has been “damn the winter weather, full speed ahead!”  And somewhat to my surprise, I managed to get the floor panels I designed (and wrote about here) completed.  Apparently after repeated exposures, my hands finally got used to working in 37°F (2.8°C) weather, and I didn’t feel cold any longer.  My ears were protected by 3M™ WorkTunes™ headphones, which may have been the single best tool investment I have yet made on this project.  Certainly the most consistently utilized, particularly with Spotify keeping my ears happy and not merely warm.

A big ($3000) order of materials was delivered in late October, and I immediately started trying to get the flooring in place.  Zephyr was intrigued.

Curious cat is curious

At first things went pretty quickly.

However, my birthday party happened just a day or two into getting the materials, so it was almost November before I really got going.  Below you can see the bracing ready for the 2x4s to come in above the PIR foam board, and the 2×6’s used for every third span (west side) and for all of the 7′ spans (east side).

Here is some of the PIR foam board in place, 2×4’s across the top and on the braces, spray foamed along edges of PIR, as well as the first batt of rockwool.

And finally here is what it looks like with all the rockwool in place.

Then I started to get the actual subfloor laid on top.  Unfortunately, not very long into this we had our first 4″ snowfall, and thereafter I was spending a lot of time with the shop-vac removing the snow and water that was stuck inside various cavities (either on top of the PIR board, or on the PT plywood bottom layer where the PIR board was not yet laid).  Furthermore, laying the tongue-and-groove subflooring with the appropriate staggered (and thus, diagonal) pattern turned out to be extremely time consuming.

It’s probably worth sharing that the necessary tools for this are one (or more) sacrificial 2×4’s and a sledgehammer.  You lay the 2×4 against the edge of the subfloor plywood (best if it’s the groove side) and whack the crap out of it to get the plywood to move across the glue and into place.  I shattered one 2×4 along the way and beat another one beyond the point of further usefulness.  Also, on occasion, you may want wood shims (used to force the tongue up into the groove) or a wonderbar weighted down with a heavy piece of PT lumber (used to force the groove plywood down onto the tongue).  Or, you could do this with more than one person, in which case, you get someone to stand on the edge to keep it aligned while you whack the 2×4.  This is definitely one of those “better done with a team” jobs.

But, in the end, I managed to get it all in place.  I still want to come back and add the house-wrap to the remaining 2/3 of the floor, to keep water out over the winter, but at least the main job is now complete!

 

Was it worth it to do all that extra complex framing for the 10% improvement in insulation?  I’m not sure – maybe not.  I’m estimating that adds up to maybe 85 BTU/hr or 25W of heating saved, whereas the remaining total loss through the floor is perhaps 875 BTU/hr or 256W.  The R-41 SIPs would have been closer to 553 BTU/hr for a savings of 94W.  (All these numbers may be lower if the equilibrium temperature in the basement is higher.)  But I learned a lot of interesting things along the way.

SIP Sliding Away

This week, I threw up my hands in frustration and did a small redesign.  I have been planning all along to use SIPs for the first floor flooring (above the basement).  Unfortunately, I have been so busy with other projects like fencing our back yard against deer and dealing with my duties as volunteer Treasurer for my community, that I didn’t actually get an order placed.  Add to this that the time frame for getting SIPs delivered turned out to be 3-4 weeks ARO (“after receipt of order”), this would have put me receiving the materials somewhere around when the average daily high temperature crosses below 50°F/10°C and the snow starts to fly.  Plus, the quotation came in about $2,000 over my budgetary estimate.  I could save some of this by using a lower insulation SIP – which would probably be OK – as the basement will generally stay closer to ground temperature than outdoor temperature, I won’t lose as much heat through the floor as through the walls.

The local code enforcement officer indicated that I needed to either get a floor in place or put up a (rather permanent-sounding) fence around the site before the winter, and I didn’t want to spend a whole lot of money on fencing if I could just get the floor on.

To top it off, I was having trouble getting a useful structural load analysis that reflected my intended usage.  Somewhere in here, while I was busy trying to compute the transverse load for a 4′ span from the modulus of elasticity of extruded polystyrene, I turned a corner.  Was this really worth going out on a limb and then jumping from treetop to treetop over?  Load tables and beam strength calculations for wooden joists were incredibly easy to come by.  And they showed that all it would take was a 2×6 member spaced every 24″1 to span over 8 feet.  Heck, even a measly 2×4 would span 5 feet.  If these were then reinforced with a bottom layer of plywood (which would effectively prevent the bottom of the beams from stretching and make them even stronger) and topped with subflooring, I would have a structurally sound flooring solution.

It would need to be insulated though.  Polyisocyanurate foam board (often abbreviated PIR) is about the best insulation density you can get in an off-the-shelf product (R-6.5 per inch) and so 4 inches of this would put me at R-26 – exactly where the cheaper SIPs would have put me.  However, that would involve a lot of cutting foam to fit around the structural members.  I was also worried about the thermal bridging from all of the wood, particularly if I needed to space the joists 16″ OC to ensure a rigid floor and not need multiple layers of subflooring to achieve it.

I finally came up with what seemed like the key innovation to me.  If a 2×4 can span over 5′ at 24″ OC or nearly 6′ at 16″ OC, then as long as it’s structurally supported every 4′ or 5′, the 2×4 can actually serve the role as a floor joist.  Adding a 2×6 for every 3rd member would increase the strength further.  The PIR foam board I was looking to use2 is 2″ thick, meaning that it would in principle fit in the difference between a 3.5″ 2×4 and a 5.5″ 2×6, and from there it would actually provide some additional support to the 2×4.  At this point I could get away with only cutting each PIR board a little bit to fit between 2×6 members, and around the supports.

But now I’m only at R-13!  That isn’t very good insulation for a potential 25°F/14°C temperature differential.  Adding batts of 3.5″ rock wool, which is exactly designed for 2×4 spaces, adds another R-15 (total R-28).  The final assembly looks something like what is shown here.

And, I should be able to start getting the parts more-or-less immediately.  And, the whole thing will probably save me some money relative to even the cheapest of the SIPS.  Some extra labor, to be sure, but the sooner I can get started on it, the more likely I am to get this done before real winter hits.

A little afterword about the R-value.  Using data on individual components I’m estimating the average R-value for the entire floor at 25.9.  It’s interesting to see that 77% of the heat loss is through the two layers of insulation; 14% of it is through the 2×6 joists; and 8% of it is through the 2×4 joists.  Thus even though the 2×6 joists account for less than 5% of the total area, they’re responsible for a significant fraction of the heat loss.  If I had used 2×6 everywhere, the R-value would have been lowered to 23.6 (almost 10% worse) and the joists would have been 30% of the loss.

 

  1. The construction terminology is 24″ OC standing for “on center” – that is, the centers of the boards are 24″ apart.
  2. I don’t really care for Dow but the appears to be the only suitable PIR I can get locally.

Time to Build, Less to Write

We’re having a big thunderstorm this afternoon.  Before this, the weather had been good enough for the past few weeks that much of the free time I might have spent blogging about the Little Rental House was instead spent building it.  This is one of the reasons things have been so quiet here lately.  The other is that I sank a whole lot of time into a long, detailed post about rainwater collection, which still isn’t finished, and so what writing I have done hasn’t gotten published.  I promise, I’ll get that one out soon.

In the mean time, a little status update:

  • The basement slab was poured on Aug 5th.
  • I now have all five of the I-beam floor supports in place and bolted down (the photo below only shows the first two).
  • The 1″ insulation around the basement walls is about 60% finished, but has slowed down because I’ve found I need to clamp the boards in place while gluing, and I only built one clamp apparatus.
  • I’ve measured, cut, and started mounting the stringers for the basement stairs.

Finishing up the slab

De Basement

On Friday Jul 12, forms went up.  Actually, first they went down, slid from truck to hole along one of the same 2x12s that were used to form up the footer.

The forms are a pretty clever thing – they have both holes in the top and bottom flanges to allow them to be stacked and linked (my walls took two 4′ courses) as well as holes through that allow for breakaway ties that connect them against the weight of the concrete pushing outward when they’re filled up.

Originally, they were planning to pour the same day, but between the availability of concrete trucks, the length of the process, and the heat, they wound up calling it off and rescheduling for Monday.  Thus, on Saturday Jul 13, I had a chance to check the work, which seemed great overall.  I also took a number of photos to provide to our local Code Enforcement Officer, since he was out during the week and wasn’t able to visit the site between the forming and the pour.

I verified a number of things like the distance from the lot lines, which all seemed OK.  I did find a pair of pipes (for utilities) that were on the wrong end of the wall, but I was able to easily put in another pair.  The two grey pipes are the ones I added.

However, by the time I was done my clothes were covered in the release oil that they had put onto the forms.  Even though this was an “eco-friendly” release agent, it smelled so strongly that Raederle had a migraine within 15 minutes and I promptly tossed the clothes in a pile outside.

On Monday Jul 15, they came back in the morning to do the pour.  As much of the work (which is a lot) is done by the concrete truck, the team still had to stir and push the concrete away from the chute and into the forms with long 2×4’s.  It was a hot (80°F/27°C) and sunny day, but not yet the peak of the week.

For the end of the pour, they used the very clever “conveyor truck” which allows them to direct the concrete just by moving around a long tube.  That let them focus their efforts on the finesse of getting it level so they could finish the top surface easily.

Then they installed the anchor bolts that will hold the house down to the foundation.

Here is what it looked like at 8pm, several hours after they finished, as the concrete was setting.

The next day, Tuesday Jul 16, they were back to take down the steel forms.  Here is what it looked like partway through at a little after 10am.

Those steel forms that were easily slid down into the hole then all had to be lifted back out and loaded onto the trucks.  A lot of hard, hot, and thirsty work, on a day that got up to 88°F (31°C) with bright sun all day.  I brought them a gallon of ice water mid day when their own reserves were running low.  And here at last, is the finished product.  I now own (well, once they cash the check) a basement!

Set In Motion, Set In Stone

Today was a big day for the Little Rental House.  Today was the day when it became rather more difficult to get cold feet and quit.  What was just a hole in the ground yesterday is concrete in the ground today.  The footers were poured.  On Friday, they expect to return to build and pour the basement walls.

Today was perhaps the hottest day of the summer so far – something like 92 degrees Fahrenheit with high humidity, so I do not envy the team who came out to do the work, despite their bronzed skin and 6-pack abs.

A few interesting steps occurred along the way.  First of all, as they were setting up the forms, they asked me to order a load of stone (“Crushed Number 2 Gravel” looks something like this, although I got it from H.L. Robinson which doesn’t have pretty pictures on their web site).  They spread this on both the inside and outside of the forms to support the weight of the concrete.  Second, I got the first formal building inspection from the Town of Danby, when they came to review the installation of the rebar inside the forms before the concrete was poured.  They included the new NEC mandated ground connection to the rebar, where an extra piece of rebar was bent so that it protrudes out of the footer to provide a place to make a ground connection.

When the truck arrived to do the pour, they had to move around the chute of the truck, and an auxiliary chute that they used kind of a little “marble run” game to redirect the concrete to various areas.  They would then push (with shovels) the concrete to get it spread out evenly from where it was being dumped. 

One fellow generally worked with the concrete “float”1 while the other was working with the truck and pushing the concrete level.  They would also sometimes stir it up by rapidly inserting and removing the shovel, which helped to get it to flow and self-level.  (It’s not clear to me whether they were taking their level more from the nails in the forms or from the concrete’s own natural flow.)

They were also going around inserting the vertical rebar which will tie the walls to the footers.  They told me that with 3 people they could generally keep up with the truck’s pour, but with just 2 they were having to switch off jobs and had to stop the truck for several minutes at a time while they caught up.  Nevertheless, the whole pour was only 1h40m of the whole footer project.

The last part of the pour they had to do with the wheelbarrow (I believe I counted 8 loads), because the reach of the truck’s chute wasn’t far enough, and their own extension chute had a broken chain so they couldn’t attach it to extend the fill the remaining distance.  But pretty quickly, the pour was finished and smooth.  Because of the heat, it was already starting to set up by the time they got around to making the two ends meet.

So, if I’d ever considered having second thoughts about embarking on this project, I think the time is now past.  We’re building a house!

 

  1. I searched google to try to figure out where that name comes from, but didn’t find any good answer.